Cost of Kinder Morgan’s Trans Mountain expansion quietly rises to $6.8 billion

By Robyn Allan November 17th 2015

The pricetag for the Trans Mountain pipeline has gotten a lot bigger. So why is Kinder Morgan keeping Canadians, and the National Energy Board, in the dark?

The preliminary capital cost for Trans Mountain’s expansion has jumped 25 per cent—from $5.4 billion to $6.8 billion. Kinder Morgan Canada president, Ian Anderson, flew down to Houston last month to ensure U.S. investor analysts were informed, but hasn’t advised any of us here in Canada.

He had a perfect opportunity at an energy conference in Calgary last week, but it seems, he missed it.

In July I wrote Kinder Morgan Inc. (KMI), Trans Mountain’s U.S. parent, to enquire about the project’s capital cost. I was sure the estimate had changed.

It was prepared in late 2012 when the Canadian dollar was roughly equivalent to its U.S. counterpart. KMI hadn’t adjusted the figure in its filings with the Securities and Exchange Commission (SEC) and Kinder Morgan Canada hadn’t adjusted the figure in its filings at the National Energy Board (NEB) here at home.

The thing is, the Canadian dollar had been significantly discounted to the U.S. dollar for some time and expectations were it would remain low. Even in “as spent dollars” it is not possible for the capital budget in U.S. and Canadian dollars to remain the same. What’s more, the Board had attached draft conditions and the in-service date had been pushed. Either the SEC or the NEB was being misled.

Attempts to obtain a response from KMI went unaddressed. Finally on September 20, 2015, a spokesperson from Kinder Morgan Canada told me not to expect answers.

In an email I was informed,“Kinder Morgan will update its cost estimates for the proposed Trans Mountain Expansion Project as per its agreements with its Shippers and regulatory requirements as per the commercial agreements filed with the National Energy Board.”

I knew what that meant. I had read the agreement. It meant Kinder Morgan had no intention of making the Canadian public, or the NEB, aware of a jump in its estimated capital cost until after it got the green light to build its project. Kinder Morgan appears to be skirting the negative implications of Trans Mountain’s increased capital cost by keeping Canadians in the dark.

More than an hour and twenty minutes into KMI’s third quarter earnings call in Texas, on October 21, Ian Anderson explained to analysts why the capital cost for Trans Mountain expansion had increased to $6.8 billion (CAD).

As far as the costs go, we’ve been reporting…um… $5.4 billion US dollars for the project for a number of quarters now and that is still a good forecast. The project was originally…um…filed with the regulator as a $5.4 Canadian dollar project so if you convert the $5.4 American, that’s about $6.8 Canadian today and a few things have driven that. Most of them scope changes to the project, foreign exchange on non-Canadian sourced goods and materials as well as the impact of the delay. So if you add those three factors together, the project is currently sitting at about a $6.8 billion Canadian forecast, or about the $5.4 billion US we have been reporting.”

The Canadian capital cost is what is important to the project’s commercial viability. It’s that cost that drives toll rates shippers will pay to send petroleum products along the existing and new pipeline once the system is expanded.

As capital costs increase, so do tolls shippers pay. If tolls exceed a certain limit, shippers can walk. As Mr. Anderson explained, “a toll to our customers in excess of $6.8 billion—that gives them the out.”

Kinder Morgan has take or pay contracts with 13 shippers—11 have signed on for 20 years and two for 15. This means that if they don’t use the capacity, they pay anyway. That’s a liability worth about $2 billion for the average shipper.

Don’t expect any of Trans Mountain’s shippers to say they want out at this point, even as they’re backing away from oil sands projects. They are under a legal obligation to speak well of the Trans Mountain’s expansion until its through the regulatory process. No matter what happens, shippers who have signed up must publicly support Trans Mountain in getting the regulatory approval it seeks. It’s in Clause 2.2 of the contract.

Screenshot of Trans Mountain’s 2012 “Facility Support Agreement”

If shippers want out, they have to wait to tell Kinder Morgan until after the Trans Mountain project is approved and the NEB has issued the Certificate of Public Convenience and Necessity (CPCN).

It’s this certificate that permits Trans Mountain to build and operate its pipeline. Within 90 days of getting the permit, Trans Mountain will deliver a CPCN Cost Estimate to its shippers along with the toll rates the new estimate triggers.

The CPCN Cost Estimate will likely end up being higher than $6.8 billion. The current budget is not as detailed an engineering estimate as the CPCN estimate must be. As well, the NEB has not finalized the conditions Kinder Morgan will be required to meet.

The pertinent issue right now, though, is where the NEB is on this issue. The Board said it would assess the viability of the project. It’s one of the few areas it deemed worthy to include in its outrageously limited scope of issues. When increased capital costs let shippers walk, the project’s viability is threatened.

Curiously, though, the Board has not questioned Trans Mountain’s capital costs, or the terms of the long term contracts—not once in almost two years. Kinder Morgan says its has binding contracts, but the Board has not seen them.

This is how the Board conveniently remains within the bounds of plausible deniability while putting the public interest at risk. Information casting doubt on Trans Mountain’s viability is considered only if it is filed on the hearing record, but the Board asks no questions to ensure it gets there.

Kinder Morgan has no legal obligation to provide the information until the Board asks the company to do so.

The Board can pretend in its report to Cabinet that the capital cost estimate is $5.4 billion CDN when it is not, and contend shippers are bound, when they aren’t.

Screenshot from Trans Mountain website still pegging costs at $5.4 billion.

This is another example of how the NEB will fail the public and why the Liberal government promise to overhaul the NEB and redo Trans Mountain’s review can’t happen soon enough.

Source: Cost of Kinder Morgan’s Trans Mountain expansion quietly rises to $6.8 billion | National Observer

UN tells feds to consult before approving B.C. coast pipelines

Report by James Anaya, the UN’s special rapporteur, says there’s a ‘crisis’ in Canada

By Peter O’Neil, Vancouver Sun May 12, 2014

UN tells feds to consult before approving B.C. coast pipelines

A report by James Anaya, the UN’s special rapporteur on the rights of indigenous peoples (pictured), said there is a “crisis” in Canada and that the level of mistrust has perhaps worsened in the past decade.     Photograph by: Sean Kilpatrick , The Canadian Press

OTTAWA — The Harper government must ensure there is “free, prior and informed consent” from First Nations before giving the go-ahead to major resource projects – including two proposed pipeline megaprojects to the B.C. coast, the United Nations said Monday.

A report by James Anaya, the UN’s outgoing Special Rapporteur on the Rights of Indigenous Peoples, said there is a “crisis” in Canada and that the level of mistrust has perhaps worsened since the last visit by a UN representative just over a decade ago.

Anaya put the two oil sands pipeline megaprojects – Enbridge’s to Kitimat and Kinder Morgan Canada’s to Burnaby – at the top of a long list of economic initiatives that have drawn bitter complaints from aboriginal leaders Anaya met during a fact-finding mission last year.

Anaya, an American indigenous rights scholar and nominee for the 2014 Nobel Peace Prize, said the government doesn’t have a coherent plan to meet its Supreme Court of Canada-mandated obligations to consult and accommodate First Nations before major projects proceed.

“There appears to be a lack of a consistent framework or policy for the implementation of this duty to consult, which is contributing to an atmosphere of contentiousness and mistrust that is conducive neither to beneficial economic development nor social peace,” Anaya wrote.

One of his recommendations calls on the federal government to set a clear policy on consultation and accommodation.

“In accordance with the Canadian constitution and relevant international human rights standards, as a general rule resource extraction should not occur on lands subject to aboriginal claims without adequate consultations with, and the free, prior and informed consent of, the indigenous peoples concerned,” stated Anaya in his report that was released in Geneva Monday.

In a Vancouver Sun interview Monday Anaya said “free, prior and informed consent,” a term used in the 2007 UN Declaration on the Rights of Indigenous Peoples, doesn’t mean there should be an Aboriginal veto on resource projects.

But he said said the commitment in the declaration, which Canada endorsed 2010, does require governments to engage in genuine consultation to ensure Aboriginal rights are protected, and to consider killing projects when accommodation can’t be reached.

The report also lists the Site C hydroelectric dam project on the Peace River, gas drilling and pipeline construction in northeastern B.C. on Treaty 8 nations’ traditional territory, and the attempts by Taseko Mines and Fortune Minerals to build mines on unceded traditional First Nations territory in B.C.

The report criticized the federal environmental review panels, saying the panelists are perceived by First Nations as having “little understanding of aboriginal rights jurisprudence or concepts.”

Anaya had a number of other tough criticisms:

– He called on the Harper to reverse his position and call for a “comprehensive, nation-wide inquiry into the issue of missing and murdered aboriginal woman and girls, organized in consultation with indigenous peoples.”

– He sharply criticized the federal government over its handing of land claims across Canada and especially in B.C., where many First Nations are deeply in debt and utterly frustrated over federal negotiating tactics.

But Anaya also found some positive developments, including the agreement late last year to establish a B.C. First Nations Health Authority. He called that a potential model for other jurisdictions.

Aboriginal Affairs Minister Bernard Valcourt cited in a statement Monday the report’s complimentary references to Canada’s track record in protecting Aboriginal peoples’ rights.

“The report published by the Special Rapporteur today acknowledges that, while many challenges remain, many positive steps have been taken by the Government of Canada to improve the overall well-being and prosperity of Aboriginal people in Canada.

He also said resource projects should be seen in a positive light.